Tuesday, August 4, 2009

Update 14 & 15: Frames complete ; Windows mounted and bricks delvered

Hello all ,

I have been bit of slack updating the blog. There has been plenty of action over last week and a half. In reality this blog should probably equivalent to two separate blogs (Hence Update 14 & 15). Our frame was complete (28 July) by Saturday (1 August) we had our windows in place mounted on to the wall frame. Add to our joy we also have our bricks delivered on site. While this was happenning on the site on saturday, we finalized our wet area tile selections . Although its going to cost us $$$ for upgrades (niche, feature wall , tiling extended up to the ceiling etc.) we are hoping its not a bombshell thrown at us when we have the quote in hand.

Needless to say are pretty exited with the progress so far (please ignore the slackness on my part not updating the blog,, but surely i feel guilty about it ) , and delighted with our design , modifications and overall structure. Here are some framing pics courtesy F+S and few pics i clicked on satuday evening ( I hope our SS is not reading the blog and cut our access to the site ) . Will promise to be more punctual with further blogs , as the action continues !! Stay tuned in.......................... !!!













Sunday, July 26, 2009

Update 13: Frames Delivered !!

We went to site this morning to meet our wisdom neighbours who took photographs for me while i was away . It was great meeting F+S , we chatted in length about our experience and stories of the exiting build process.

To top up the joy meeting our to be new neighbours, we also found out our frames and roof trusses have been delivered . Yippeee !!! Lights , camera and action................. !!!










Sunday, July 19, 2009

Update 12 : Bring it on !! slab done ready for the frame :

On monday 13th July our slab was done and our wonderful neighbours sent us pretty pictures to celebrate the milestone with a virtual slab dance!! I am finally back home and first thing we was to greet our new slab welcome in person. The slab looks fantasti , well cured and all ready for the frame now !! Bring it on !!!!!!!!!















Monday, July 13, 2009

Update 11: some more pics

Some more pics of waffles !! Rain dont spoil the waffle's date with concrete , please !!!




















Saturday, July 11, 2009

Update 10: Concrete come soon !! I am waiting for you my love !!

Waffles all ready decked up for a date with the concrete !! Oh , by the way we also have the port-a-loo and the recycling sack !!!







Friday, July 10, 2009

Update 9 : Waffle Pods

We got call from our SS - F today and also few more pics from the friends . Despite the wheat her , the work is progressing full steam ahead. The waffle pods are in progress and we are simply loving it !! Some great pics , courtesy neighbours !!




















Wednesday, July 8, 2009

Update 8 : woohooo !! Drilling for piers

Thanks to our wonderful paparazzi neighbours , we have progress update to share. The drilling crew and port-a -loo are -site working hard to help us catch up with fellow wisdomites to slab stage . Here are some of the pics, courtesy our lovely neighbours. Thank you neighbours, we are grateful to you !!